NO.1 You are the Test Manager for a project to develop a client-server application that allows wine
vendors to order custom-assorted packages of wines of several winemakers to sell special packages
in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the
system testinG. EXCR1- Each "critical" quality risk item must be covered by at least one test
condition EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and
no more bottles than the package size. No error messages shall be displayed if the user selects a
valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid
number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card
data are given by the user
QUSTION NO: 11 The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed
to get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order TC-CR-RSK-1. Test the accepted values from
the input field designed to get the number of bottles from the user
Assume that you have used traceability to determine the logical test cases that cover all the
requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the
REQSEL-4 requirement?
K3 2 credits
A. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are
displayed
B. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
C. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles"
message is displayed
D. Select a 6-bottles package, then try to insert 7 bottles
Answer: C

ISQI参考書勉強 CTAL-TM_Syll2012好評 CTAL-TM_Syll2012的中率

NO.2 Which of the following is an example of the test closure activity indicated as "lessons learned"?
K2 1 credit
A. Archive all the test results of the acceptance testing phase
B. Deliver a list of the open defects of a software product released into production to the service
desk team
C. Participate in a meeting at the end of a project aimed at better managing the events and
problems of future projects
D. Deliver an automated regression test suite, used during the system test phase of a software
product released into production, to the team responsible for maintenance testing
Answer: C

ISQI評判 CTAL-TM_Syll2012実際試験 CTAL-TM_Syll2012 CTAL-TM_Syll2012教科書

NO.3 The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at
least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No
known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
K2 1 credit
A. A traceability matrix showing the relationships between the product risk items and the test cases
B. A list of all the open defects with the associated classification information extracted from the
defect tracking system
C. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the
defect tracking system
D. The execution status of all the test cases extracted from the test management tool
Answer: C

ISQI前提条件 CTAL-TM_Syll2012オフィシャル CTAL-TM_Syll2012ラーニング CTAL-TM_Syll2012全真問題集

NO.4 Consider an information system of a Pay-Tv company based on a SOA architecture.
The integrated system currently consists of three core systems:
-a CRM (Customer Relationship Management) system
-a BRM (Billing and Revenue Management) system
-a CAS (Conditional Access System) system all of them communicating with SOA Middleware.
You have been asked to manage the testing activities for the integration of two additional
off-theshelf systems from two different vendors: a SMS (Short Message Service) server and an IVR
(Interactive Voice Response) system.
Assume that there is a high likelihood that the two off-the-shelf systems will be low-quality and that
you have a clear proof that the testing performed by the two vendors on their systems has been
unsystematic and unprofessional. This obviously leads to higher quality risk for the overall
integrated system.
You are the Test Manager of this project. Your main goal is to plan for testing activities to mitigate
this risk.
Which of the following answers best describes the test activities (assuming it is possible to perform
all of them) you should plan for?
K4 3 credits
A. You should plan for an informal and minimal acceptance test of the two off-the-shelf systems and
then a single end-to-end test of the overall integrated system
B. You should directly plan for a single end-to-end test focused on end-to-end tests of the overall
integrated system without an acceptance test of the two off-the-shelf systems
C. You should plan for two levels: a system integration test and an end-to-end test of the overall
integrated system
D. You should plan for adequate re-testing of both the systems followed by a system integration test
and an end-to-end test of the overall integrated system
Answer: D

ISQI内容 CTAL-TM_Syll2012 CTAL-TM_Syll2012 CTAL-TM_Syll2012

NO.5 Assume you are the Test Manager for a new software release of an e-commerce application.
The server farm consists of six servers providing different capabilities. Each capability is provided
through a set of web services.
The requirements specification document contains several SLAs
(Service Level Agreements) like the following:
SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a
load of up-to 5000 concurrent users
The main objective is to assure that all the SLAs specified in the requirements specification
document will be met before system release. You decide to apply a risk-based testing strategy and
an early risk analysis confirms that performance is high risk. You can count on a well-written
requirements specification and on a model of the system behavior under various load levels
produced by the system architect.
Which of the following test activities would you expect to be the less important ones to achieve the
test objectives in this scenario?
K4 3 credits
A. Perform unit performance testing for each single web service
B. Monitor the SLAs after the system has been released into the production environment
C. Perform system performance testing, consisting of several performance testing sessions, to verify
if all the SLAs have been met
D. Perform static performance testing by reviewing the architectural model of the system under
various load levels
Answer: B

ISQI CTAL-TM_Syll2012対応 CTAL-TM_Syll2012市販本 CTAL-TM_Syll2012初心者

NO.6 You are the Test Manager for a project to develop a client-server application that allows wine
vendors to order custom-assorted packages of wines of several winemakers to sell special packages
in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the
system testinG.
EXCR1- Each "critical" quality risk item must be covered by at least one test condition
EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and
no more bottles than the package size. No error messages shall be displayed if the user selects a
valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid
number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card
data are given by the user
The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to
get the number of bottles from the user Test analysis for system testing has just begun and the
following test conditions have been identified.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles
from the user
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 4
B. 3
C. 2
D. 1
Answer: A

ISQI CTAL-TM_Syll2012 CTAL-TM_Syll2012 CTAL-TM_Syll2012認証

NO.7 Which of the following statements describing the consequences of specifying test conditions
at a detailed level is NOT true?
K2 1 credit
A. In an environment where the test basis is continuously changing, it is recommended to specify
test conditions at a detailed level in order to achieve a better maintainability
B. The specification of test conditions at a detailed level can be effective when no formal
requirements or other development work products are available
C. The specification of test conditions at a detailed level can require the implementation of an
adequate level of formality across the team
D. For system testing, the specification of test conditions at a detailed level, carried out early in the
project as soon as the test basis is established, can contribute to defect prevention
Answer: A

ISQI試験感想 CTAL-TM_Syll2012オフィシャル CTAL-TM_Syll2012テスト CTAL-TM_Syll2012クラムメディア

NO.8 The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to
define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit
voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the
available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the
accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the
"select" and "purchase" pages going back to the "browse" page (anonymous navigation)
Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time (less than
10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 1
B. 2
C. 3
D. 4
Answer: C

ISQI教育 CTAL-TM_Syll2012教本 CTAL-TM_Syll2012試験感想 CTAL-TM_Syll2012好評



インターネットで高品質かつ最新のISQIのCTAL-TM_Syll2012の試験の資料を提供していると言うサイトがたくさんあります。が、サイトに相関する依頼できる保証が何一つありません。ここで私が言いたいのはPass4Testのコアバリューです。すべてのISQIのCTAL-TM_Syll2012試験は非常に重要ですが、こんな情報技術が急速に発展している時代に、Pass4Testはただその中の一つです。では、なぜ受験生たちはほとんどPass4Testを選んだのですか。それはPass4Testが提供した試験問題資料は絶対あなたが試験に合格することを保証しますから。なんでそうやって言ったのはPass4Testが提供した試験問題資料は最新な資料ですから。それも受験生たちが実践を通して証明したことです。

現在、IT業界での激しい競争に直面しているあなたは、無力に感じるでしょう。これは避けられないことですから、あなたがしなければならないことは、自分のキャリアを護衛するのです。色々な選択がありますが、Pass4TestのISQIのCTAL-TM_Syll2012問題集と解答をお勧めします。それはあなたが成功認定を助ける良いヘルパーですから、あなたはまだ何を待っているのですか。速く最新のPass4TestのISQIのCTAL-TM_Syll2012トレーニング資料を取りに行きましょう。

Pass4Testは異なるトレーニングツールと資源を提供してあなたのISQIのCTAL-TM_Syll2012の認証試験の準備にヘルプを差し上げます。編成チュートリアルは授業コース、実践検定、試験エンジンと一部の無料なPDFダウンロードを含めています。

21世紀の情報化時代の急流の到来につれて、人々はこの時代に適応できるようにいつも自分の知識を増加していてますが、まだずっと足りないです。IT業種について言えば、ISQIのCTAL-TM_Syll2012認定試験はIT業種で欠くことができない認証ですから、この試験に合格するのはとても必要です。この試験が難しいですから、試験に合格すれば国際的に認証され、受け入れられることができます。そうすると、美しい未来と高給をもらう仕事を持てるようになります。Pass4Testというサイトは世界で最も信頼できるIT認証トレーニング資料を持っていますから、Pass4Testを利用したらあなたがずっと期待している夢を実現することができるようになります。100パーセントの合格率を保証しますから、ISQIのCTAL-TM_Syll2012認定試験を受ける受験生のあなたはまだ何を待っているのですか。速くPass4Testというサイトをクリックしてください。

試験番号:CTAL-TM_Syll2012
試験科目:「ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]」
一年間無料で問題集をアップデートするサービスを提供いたします
最近更新時間:2015-04-22
問題と解答:全64問 CTAL-TM_Syll2012 関連資料

>>詳しい紹介はこちら


あなたに最大の利便性を与えるために、Pass4Testは様々なバージョンの教材を用意しておきます。PDF版のCTAL-TM_Syll2012問題集は読みやすくて、忠実に試験の問題を再現することができます。テストエンジンとして、ソフトウェア版のCTAL-TM_Syll2012問題集はあなたの試験の準備についての進捗状況をテストするために利用することができます。もし試験の準備を十分にしたかどうかを確認したいなら、ソフトウェア版のCTAL-TM_Syll2012問題集を利用して自分のレベルをテストしてください。従って、すぐに自分の弱点や欠点を識別することができ、正しく次のCTAL-TM_Syll2012学習内容を手配することもできます。

Pass4Testは高品質の製品を提供するだけではなく、完全なアフターサービスも提供します。当社の製品を利用したら、一年間の無料更新サービスを提供します。しかも、速いスピードで受験生の皆様に提供して差し上げます。あなたがいつでも最新の試験資料を持っていることを保証します。

Pass4Testは最新のC_SRM_72試験問題集と高品質のHP0-J62認定試験の問題と回答を提供します。Pass4TestのC2010-940 VCEテストエンジンと4A0-101試験ガイドはあなたが一回で試験に合格するのを助けることができます。高品質のM2010-719トレーニング教材は、あなたがより迅速かつ簡単に試験に合格することを100%保証します。試験に合格して認証資格を取るのはそのような簡単なことです。

記事のリンク:http://www.pass4test.jp/CTAL-TM_Syll2012.html


同じカテゴリー(ISQI)の記事
 ISQIのCTAL-TA_Syll2012認定試験の復習問題集 (2015-04-23 12:54)
 ISQI IREB認定試験に適する最高の問題集を捧げる (2014-12-16 12:25)
 ISQI IREB-IT-CQ03認定試験に関連する最も優秀な問題集 (2014-12-05 11:42)
 CTAL-TA_Syll2012学習資料、CTAL-TM_Syll2012学習教材 (2014-07-03 12:01)

Posted by passfortest at 12:52│Comments(0)ISQI
上の画像に書かれている文字を入力して下さい
 
<ご注意>
書き込まれた内容は公開され、ブログの持ち主だけが削除できます。